TITAN
- From 03.2016 to 19.12.2016 Dismantling of the existing steel structure and installation of a new steel structure
- From 11.2016 to 19.12.2016 Delivery and installation of mechanical anchors and steel structure
- From 10.2017 to 20 .12.2017 Civil Repair Works on brick walls and dismantling of metal structures in Heat Exchange Tower and Raw Materials Mills
- From 31.10 .2017 to 13.07.2018 Renovation of bypass pedestrian bridges and connections between the roofs of cement silos
- From 12.2017 to 26.06.20178 Replacement of expansion joints gas duct between exhaust Fan 5 and Cooling Tower of chamber 5
- From 12.2017 to 18.04.2018 Delivery and installation of steel structure of gas duct of Cooling Tower 5
- From 12.2018 to 20.12.2018 Replacement of worn out part of gas duct
- From 04.2019 to 10.07.2019 Bag filter
- From 11.2019 Repair activities of cement silo of concrete knot Military Rump
- From 11.2019 to 17.02.2020 Expansion joint replacement
- From 12.2019 to 5.12.2019 Repair of grate cooler
- From 01.2020 to 30 .10. 2020 Construction of new transport of raw material to storage silos № 3 and № 4
- From 02.2020 to 30.10.2020 Fabrication, delivery and installation of steel pyramid inside storage silo 3
- From 02.2020 to Alternative fuel installation
- From 01.2020 Internal cleaning of silos 1, 2, 3, 4